Busway / busduct monitoring
Data centres, high-rise commercial buildings, hospitals, metro systems and large factories
The sensing fibre runs along the full length of the busway, including every joint and tap-off. Loose or oxidised joints show up as a local temperature rise against the neighbouring sections, long before insulation damage or a busway fire. One controller covers up to 4 busway risers or runs.
Engineering note
A busway joint hotspot is short. With 0.5 m spatial resolution, DTS will show it, but it will read lower than the true contact temperature. Alarms should therefore be set on temperature rise against adjacent sections and on rate of rise, not on absolute value alone. For the most critical joints and tap-off units we recommend combining DTS with VTI point sensors.
Recommended for busway: DTS for the route + point sensors for the critical joints.